G98 and G99 are the Energy Networks Association rules for connecting generation and batteries to the local network. G98 covers fully type tested kit up to and including 16A per phase, and for a single home you can usually fit it and tell the network operator within 28 days. Anything bigger falls under G99, where in most cases you apply to the network operator and wait for their answer before you install.
The line between them
So the whole thing turns on one number, 16A per phase. The ENA's G98, Issue 2 covers micro-generators up to and including 16A per phase that are fully type tested, and it says anything over 16A per phase goes through G99. On a normal 230V single phase supply, 16A works out at about 3.68kW. On three phase it's 16A on each phase.
The bit people miss is that it's the total that counts. G98 looks at the combined capacity of everything generating at the property. So a 3.6kW solar system on its own might be a G98 job, and then the customer comes back a year later wanting a battery, and now the total is over 16A per phase and it's a G99 job.
Both documents are dated 10 March 2025 and both are written for Great Britain. If you work in Northern Ireland, check with the network operator there before you rely on any of this.
G98, fit first and tell them after
For a single home, G98 is what people call connect and notify. The legal side comes from the electricity safety regulations, and G98 says the installer has to make sure the DNO knows about the installation no later than 28 days after commissioning, counting the day of commissioning. The details go on the G98 Installation Document, which the ENA calls Form B. More and more of this is done online now, and if you use the ENA's Connect Direct platform you also send a clear photo of the cut-out so it can be checked.
There's one catch. If you're putting in micro-generators at several properties close together, or you've done others nearby in the last 28 days or plan to in the next 28, the single home route doesn't apply. That's the multiple premises procedure. You talk to the DNO early, send an application in the Form A format, and you can't connect until they've approved it and done any work they need to do. Then you still confirm commissioning within 28 days.
Issue 2 of G98 also added new requirements for micro-generators that include battery storage, which came into force on 1 March 2026. If you fit batteries, make sure the kit you're buying is tested to the current issue.
G99, usually apply first
The ENA's G99, Issue 2 covers everything that doesn't fit G98. For a big commercial system that means a proper application, studies by the DNO and sometimes witness testing. But for homes and other small low voltage jobs, G99 has three small generation installation procedures, and they only apply where all the existing and new generating units add up to no more than 32A per phase of design capacity.
| Route | Rough rule of thumb | What you do |
|---|---|---|
| G98 | Everything adds up to 16A per phase or less, fully type tested | Fit it, then send the installation document within 28 days |
| G99 SGI-1 | No unit over 32A, anything over 16A limited to 16A, total no more than 16A per phase | Fit and commission, then send the notification form |
| G99 SGI-2 | Each unit limited to 16A, total under 32A per phase, export limited to 16A per phase | Apply first, and the DNO gives you an answer within 10 working days |
| G99 SGI-3 | Units up to 32A each, total under 60A per phase, export limited to 32A per phase | Apply first, and within 10 working days the DNO tells you if it needs to look further |
| G99 standard | Anything outside those routes | Full application to the DNO before you install |
That table is a summary to help you see the shape of it. The conditions in G99 itself are more detailed than this, so read the document before you rely on a route for a job.
G99 says SGI-2 is basically the old integrated micro generation and storage procedure from earlier versions, so if you used that before, this is where it went. A few details matter. The export limit has to be a fully type tested G100 export limitation scheme. Nothing gets installed or commissioned until the DNO's told you the outcome. The planned commissioning date on the form has to be between 10 working days and three months from when you apply. Then you confirm commissioning within 28 days.
A worked example
Say you've got 20 engineers and you do around 50 jobs a month, a mix of solar on its own, solar with batteries, and batteries added to existing solar. Maybe half go through G98 and half go through one of the G99 routes. Rough numbers, but you get the point.
That's 25 jobs a month with a 28 day notification deadline after commissioning, and 25 where you can't even book the install until the DNO has replied. The G99 ones are where the money gets stuck. The customer's paid a deposit, the kit's in the warehouse, and the job can't go in the diary because nobody's chased the application. And if the planned commissioning date on the form was more than three months out, you're starting again.
The biggest thing I'd look at is whether your office can see, for every job, which route it's on, when the application went in, when the answer came back and when the 28 days run out after commissioning. If that's sitting in somebody's inbox, some of them are going to slip, especially in a busy month.
Where Agentryx One fits, honestly
We should be clear. Agentryx One doesn't fill in G98 or G99 forms, submit anything to the DNO or work out which route a job is on. Your designer still does that, and specialist solar tools handle a lot of the forms.
What we do cover is the rest of the job around it. The AI receptionist answers your number when the office can't and books surveys into the diary. Quotes can go out as good, better and best options. Jobs get planned with a planner signing them off, and your engineers use the field app for photos, checklists and signatures on site, even with no signal. Invoices go into your own Xero, Sage or QuickBooks with a pay link and get chased at 7, 14 and 30 days.
If you're MCS certified, the other half of the paperwork is in our MCS paperwork checklist. There's more on how the whole thing looks for your kind of business on the energy installers page, and how jobs get planned is on the scheduling and dispatch page.
If you want to see it on one of your own jobs, you can book a demo.