On this page
- 01Read this first
- 02How to size a cable, step by step
- 03A cable sizing example with made-up factors
- 04How to work out volt drop with the mV/A/m method
- 05How to check maximum Zs
- 06When you need design software instead
- 07Where Agentryx One fits
- 08How pricing works for Agentryx One
- 09Frequently asked questions
Read this first
We've left every table value out of this page on purpose. The current-carrying capacities, the correction factors, the mV/A/m figures and the maximum Zs values are all in BS 7671, the IET Wiring Regulations, and the current edition is BS 7671:2018+A4:2026. They're copyright, they change between amendments, and a figure copied off a website is how mistakes end up in a consumer unit.
So use this page to understand the order of the sums. Then get the numbers from your own copy of the regulations or the IET On-Site Guide, and have the design checked by a competent person. Any figure below that looks like a table value is made up for the example and is labelled that way.
How to size a cable, step by step
- Work out the design current, Ib. That's the current the circuit will actually carry. For a single-phase load it's the power divided by the voltage, and for loads that aren't purely resistive you divide by the power factor as well. For three-phase it's the power divided by the square root of three, times the line voltage, times the power factor.
- Pick the protective device rating, In, so it's equal to or bigger than Ib. The overload rules that link Ib, In and the cable's capacity are in Chapter 43 of BS 7671.
- Find the correction factors for the way this cable's installed. There's one for ambient temperature, one for grouping with other circuits, one if it runs through thermal insulation, and one if the circuit's protected by a rewireable fuse. Appendix 4 of BS 7671 has most of them, and the thermal insulation ones are in Chapter 52.
- Divide In by all the correction factors multiplied together. The answer is the minimum tabulated current, It, the cable has to have.
- Look up the current-carrying capacity tables in Appendix 4 for your cable type and installation method, and pick the smallest cable whose tabulated rating is at least It.
- Check volt drop for that cable over the actual length. If it's over the limit, go up a size and check again.
- Check fault protection. The earth fault loop impedance has to be low enough for the device to disconnect in time, and the protective conductor has to be able to take the fault current, which is the adiabatic check in Chapter 54.
A cable sizing example with made-up factors
Say it's a 32 A circuit with a design current of 28 A. The correction factors below are invented to show the sum. They aren't from BS 7671, so look up the real ones for your installation.

| Step | Example figure | Working |
|---|---|---|
| Design current, Ib | 28 A | From the load |
| Device rating, In | 32 A | In is at least Ib |
| Ambient temperature factor | 0.9 (made up) | From Appendix 4 in real life |
| Grouping factor | 0.8 (made up) | From Appendix 4 in real life |
| Thermal insulation factor | 1 (none in this example) | Not touching insulation |
| Minimum tabulated current, It | 32 ÷ (0.9 x 0.8 x 1) | 44.4 A |
| Cable | The smallest one rated at 44.4 A or more | From the Appendix 4 table for that cable and method |
How to work out volt drop with the mV/A/m method
The tables in Appendix 4 give each cable a volt drop figure in millivolts per amp per metre. You multiply that by the design current and the length of the run, then divide by 1,000 to turn millivolts into volts.
So the sum is volt drop in volts equals mV/A/m, times Ib, times length in metres, divided by 1,000. To see it as a share of the supply, divide by the supply voltage and times by 100. Use the single-phase figure for a single-phase circuit and the three-phase figure for three-phase, because the tables list them separately.
| Step | Example figure | Working |
|---|---|---|
| Cable volt drop | 10 mV/A/m (made up) | From Appendix 4 in real life |
| Design current, Ib | 20 A | From the load |
| Length of run | 25 m | Measured on site |
| Volt drop | 10 x 20 x 25 ÷ 1,000 | 5 V |
| As a share of a 230 V supply | 5 ÷ 230 x 100 | About 2.2% |
Then compare it with the volt drop limits in Appendix 4, which are different for lighting and for other uses. We haven't printed them here, check the current edition.
How to check maximum Zs
Zs is the earth fault loop impedance for the circuit. You work it out as Ze, the part outside the installation, plus R1 plus R2, the resistance of the line conductor and the protective conductor out to the furthest point. On a new circuit you can estimate R1 plus R2 from the resistance per metre of the conductors and the length. On an existing one you measure it.
Then you compare Zs with the maximum for that exact device, by type, rating and disconnection time. Those maximum values are in Chapter 41 of BS 7671. A reading taken with a cold cable reads lower than the same cable carrying load, so there's a method for comparing measured values with the tables, and the IET says the rationale behind maximum Zs values has been amended in the current On-Site Guide. Use the current edition and Guidance Note 3 for how to compare them.
Say Ze is 0.35 ohms and R1 plus R2 is 0.6 ohms, both made up. Zs is 0.95 ohms, and that's the figure you'd check against the maximum for your device.
When you need design software instead
These sums are fine for a single final circuit. For a full board schedule, sub-mains, three-phase distribution or anything with a lot of grouping, a proper design package is the safer way to do it. It does every circuit, keeps the working, and prints it for the file.
And it's not something to do from a web page if you're not trained. If you're a homeowner wanting to know what cable a shower needs, the answer is get a registered electrician to design and install it.
Where Agentryx One fits
We don't do the design calcs. Where we come in is after the work, when the readings need writing up. Engineers fill in the certificates on their phone, even with no signal. The EICR is done circuit by circuit to the BS 7671 model form, and there's the EIC and minor works too. That's on the EICR app page and in the field app.
Then faults found on a test go onto a repair quote with photos the same day, and certificates coming due text the customer to book. If you're checking a customer's dates, the EICR due checker does that sum, and the whole trade setup is on job management software for electrical contractors.
How pricing works for Agentryx One
These methods are free to use. Agentryx One doesn't have published prices. It depends on how many sites and people it covers, and you see it working at one site before you pay for the rest. There's more on how the market prices this kind of software on how much job management software costs.
Frequently asked questions
What size cable do I need for a 32 A circuit?
There isn't one answer. It depends on the installation method, the ambient temperature, grouping, insulation, the length of the run and the device. Work through the steps on this page with the values in Appendix 4 of BS 7671, and have a competent person check it.
What is the volt drop formula?
Volt drop in volts is the cable's mV/A/m figure, times the design current, times the length in metres, divided by 1,000. The mV/A/m figures and the limits are in Appendix 4 of BS 7671.
Where do I find maximum Zs values?
In Chapter 41 of BS 7671, by device type, rating and disconnection time. The On-Site Guide and Guidance Note 3 explain how to compare a measured reading with them.
Why don't you list the table values?
They're copyright, they change between amendments, and a number copied off a web page is easy to get wrong. The regulations are the only place to take them from.
Does this replace the On-Site Guide?
No. It explains the order of the sums. You still need the On-Site Guide or BS 7671 for the values, and a competent person to check the design.
How much does Agentryx One cost?
There's no published price. It depends on how many sites and people it covers, and you see it working at one site before you pay for the rest.
Does Agentryx One check my cable calcs?
No. It's for the job, the certificates, the repair quotes and the invoices. Design calcs stay with your engineers and your design software.