On this page
The EICR template
Copy this into a spreadsheet or a Word doc, or print it and take it on site. The section names follow the layout of the IET's BS 7671 model forms, but the wording in the columns is ours.
| Section | What you fill in | Tip |
|---|---|---|
| Details of the client | Name and address of the person or company ordering the report | Often the landlord or the agent, not the person living there |
| Details of the installation | Address, who occupies it, what kind of premises, estimated age of the wiring, any signs of changes, date of the last inspection if known | Ask for the last report before you go |
| Purpose of the report | Why it's been asked for, such as a tenancy, a sale, an insurance request or a routine check | The purpose often decides how far you go |
| Extent and limitations | What you inspected and tested, what you didn't, and why. Agreed limitations with the client and anything you found you couldn't get to on the day | Agree this before you start and write who agreed it |
| Summary of the condition | The general condition of the installation in plain words and the overall assessment, satisfactory or unsatisfactory | Fill this in last |
| Recommendations | When the next inspection should be and what needs doing first | Match it to the codes you've given |
| Declaration | Who inspected, who authorised the report, signatures, dates, your company and scheme details | Check the scheme number is right |
| Observations | Each item found, where it is, and a code (C1, C2, C3 or FI) | One line per item, with a photo reference |
| Supply characteristics and earthing | System type, number and type of live conductors, nominal voltage and frequency, prospective fault current, external earth fault loop impedance, supply protective device | Write down how you got each value |
| Particulars of the installation at the origin | Means of earthing, earth electrode if there is one, main switch or circuit breaker, earthing conductor, main protective bonding to water, gas and other services | Note sizes and where the bonding connects |
| Schedule of inspections | Each inspection item ticked, marked not applicable, or coded | Don't leave blanks, use N/A or LIM |
| Schedule of circuit details | Every circuit on each board, with its description, wiring type, reference method, number of points, conductor sizes and protective device | Do one schedule per distribution board |
| Schedule of test results | Continuity, insulation resistance, polarity, earth fault loop impedance and RCD test results for each circuit, plus the test instruments used | Record serial numbers of your test kit |
What the observation codes mean
This is the part customers read first, so it's worth being clear. NAPIT's Codebreakers guide goes through how to code individual items if you want more detail.

| Code | What it means | Effect on the report |
|---|---|---|
| C1 | Danger present, someone could get hurt now | Unsatisfactory, make it safe straight away |
| C2 | Potentially dangerous, needs putting right urgently | Unsatisfactory |
| C3 | Improvement recommended, but not unsafe as it stands | Doesn't make it unsatisfactory on its own |
| FI | Further investigation needed without delay | Unsatisfactory until it's looked into |
How to fill it in, in the order you'd actually do it
So the first thing is the paperwork before you go. Get the client details, the address, the purpose and the last report if there is one, and agree the extent and limitations with whoever's ordering it. A lot of arguments later come from nobody writing down that the loft wasn't accessible.
Then on site you'd usually start with the supply and the origin, because you need the earthing arrangements and the external loop impedance before the circuit results make sense. After that it's the inspection schedule and then the circuit details and test results, one board at a time.
Write the observations as you find them, with where they are and a photo. And then the summary and the overall assessment go in at the very end, once you've seen everything. If you write the summary first you end up changing it.
The IET page says you can use and electronically change its model forms for your own contracting work, but not copy blank forms to sell. Read the terms on that page before you build your own version.
When this template isn't enough
This is a checklist and a planning sheet. It isn't the certificate. If you're registered with NICEIC, NAPIT or another scheme, issue the report on your scheme's form or software. NICEIC's certification page explains what they provide for registered businesses, and the IET publishes the model forms themselves.
It also stops working once you've got a lot of engineers. Say you've got 25 engineers doing three or four EICRs a week each. That's paper or spreadsheets coming back to the office from every van, someone typing up the observations, and the C2s sitting in a pile waiting for a repair quote.
Or do it on the phone in Agentryx One
In Agentryx One your engineers fill in the EICR on their phone, circuit by circuit, to the BS 7671 model form. It works with no signal and syncs later. You can see how that works on the field app page.
The faults found on the test, such as C2s, go onto a repair quote with the photos the same day. Your team sets the price, the AI doesn't. The customer ticks the repairs they want online and each tick becomes a booked job. The full flow is on EICR remedial quotes. And when the next one's coming due, the customer gets a text with a link to pick a time. The EICR due checker helps you work out the dates.
Tradify and Joblogic both have EICRs too. As of November 2026, from their websites, Tradify has a free EICR template page and a long list of certificate forms, and Joblogic has a free Electrical Industry Pack with EICR, EIC and emergency lighting certificates. If you're a small firm and want a certificate tool you can set up yourself, either of those is a sensible place to look.
How pricing works
The template on this page is free. Agentryx One doesn't have published prices. It depends on how many sites and people it covers, and you see it working at one site before you pay for the rest. There's more on how this market prices things in how much job management software costs.
Frequently asked questions
Is this EICR template free to use?
Yes. Copy the table into whatever you use. It's a layout of the sections, written in our own words, so you can plan the job and check nothing's missing.
Can I hand this over as the EICR certificate?
No. Use the IET model form or your scheme's form for the report you give the customer. This template is for planning and checking.
Where do I download the official EICR form?
The IET publishes the BS 7671 model forms on its website, and NICEIC and NAPIT give registered businesses their own versions. Check which edition of BS 7671 the form is for before you use it.
What makes an EICR unsatisfactory?
Any C1, C2 or FI on the report makes the overall assessment unsatisfactory. C3 items on their own don't.
How much does Agentryx One cost for EICRs?
There's no published price. It depends on how many sites and people it covers, and you see it working at one site before you pay for the rest.
Is this the same as the Tradify EICR template?
They're both free layouts of the same report. Tradify's links to their own certificate software. Ours links to Agentryx One, where the engineer fills it in on the phone and the faults go straight onto a repair quote.
Can engineers fill in an EICR on a phone with no signal?
In Agentryx One, yes. It's filled in circuit by circuit and syncs once they're back in signal.